SM – Galvan G12/G13 CDP Upgrades

  • Home
  • /
  • SM – Galvan G12/G13 CDP Upgrades

Project Overview

Client / Owner:

SM/ETC

Project Duration:

April 24th 2024 - Oct. 28th 2024

Statistics:

HOURS 19,440 / TRIR 0.00

SM Galvan G12/G13 CDP Upgrades

Project Overview

L7 Oilfield & Pipeline Construction was awarded the contract to execute a comprehensive upgrade of the SM Galvan G12/G13 Central Delivery Point (CDP) facilities. The project aimed to enhance production capacity, modernize infrastructure, and expand storage capabilities. Key deliverables included building a foundation for a new heater, upgrading piping systems to support higher flow rates, and expanding the site’s containment area for additional tanks.

Scope of Work

1. Heater Installation

  • Constructed a reinforced concrete foundation for the new heater to ensure stability and longevity.
  • Fabricated and installed all necessary piping to integrate the heater into the existing system, making it operational and compliant with safety and performance standards.

2. Fuel Skid Upgrades

  • Upgraded inlet and outlet piping on the fuel skid from smaller-diameter lines to improve flow capacity and meet increased production demands.
  • Installed a fuel gas coalescer alongside the fuel skid to enhance the separation of impurities, ensuring cleaner fuel delivery to the system.

3. Booster Pumps Installation

  • Installed new booster pumps to improve pressure and flow rates, enhancing the overall efficiency of the production system.
  • Integrated booster pumps into the site’s upgraded piping network for seamless operations.

4. Tank Battery Piping Upgrades

  • Replaced all existing tank battery piping, increasing the diameter from 4” to 8” to handle higher production volumes.
  • Ensured the upgraded piping adhered to ASME and API standards, allowing for safe and efficient handling of increased throughput.

5. Containment Area Expansion

  • Expanded the containment area to create space for the installation of two additional storage tanks.
  • Constructed new containment barriers to ensure safety and compliance with environmental regulations.

Challenges Overcome

  • Tight Timeline: Despite the complexity of the upgrades, L7 effectively managed resources to stay on schedule.
  • Infrastructure Integration: Upgrading existing systems required precise coordination to avoid operational disruptions during construction.
  • Safety Standards: Maintained a spotless safety record (TRIR 0.00) by adhering to strict protocols and providing on-site training for all personnel.

Outcome

We successfully delivered a fully upgraded and operational G12/G13 CDP facility, meeting all client requirements for increased production and capacity. The project improved system efficiency, expanded storage capabilities, and ensured compliance with industry and environmental standards.